Work in progress for the new breakwater of Genoa

Work in progress for the new breakwater of Genoa

Work in progress for the new breakwater of Genoa: 40% of the planned gravel laid, exceeding 1 million tons.

Next phase: prefabrication of the caissons starting from April.  Underwater war debris clearance at 70%, focused on the last area, expected to be completed by summer.